Some Key Dates and Events

Note:   This is based on information found in various records

             and is not meant to be an exhaustive listing of events.

Year Month

                           Description

Comment

1860

 

Dam was constructed under supervision of Cushing & DeWitt

 Details;  Length= 475',  Height= 20',

Hgt above level of full pond= 5',   Avg depth of water= 10',

Length of rollway= 25'

West Dike: Length= 310',  Height= 10',  Width= 25'

> 150 years old

1886   Stated in 1933 report that the   "...Feb 12-15, 1886 storm resulted in the water level rising by 6 feet in that brief period."  
1868 1920 Ten events recorded with level over 4" above the old spillway >  11.5' lake level
1924   Ordered that water level to be kept low until repairs are made  
1927   Report states that water level has been kept low for past four years and that a lower level was ordered until repairs were made.  Owner agreed to keep water level to 7 feet below the spillway ~ 4' lake level
1928 Dec Ordered that water level to be kept at least 5.5' below the spillway.  Also, a gauge was ordered to be placed at the gate house. ~ 5.5' lake level
1929 May Ordered to comply with 5.5' below spillway prior order.    
1929   Request made "…so that a level of about 9' (or 3' below the spillway) be maintained during the summer months instead of the the 5' or 6' that now prevails…" ~ 8' lake level
1933   Records which start with 1867 through 1928 indicate that the reservoir was drawn upon each year to its entire capacity and that by August or September of most years it was completely exhausted.  
1934   First time written rules for water level during different periods of the year.     For the April-Aug period, the max allowed level was set at 3' below the spillway. ~ 8' lake level
1938 Sept

One of the worst hurricanes to hit Rhode Island.   Local resident remembers seeing the lake level being 1' or  2' below the floor of the bridge 

   (Link to 8 part video)

~15' to 16' lake level
1939   Repairs were made to the control structure repair
1943   Report suggests that level be kept about 4' below the spillway  
1976   Constructed a new bridge across the spillway bridge
1983   Trash rack was replaced, cleared brush & trees, & repaired rip-rap repair
1985   Built cinder block house & added fencing  
1992 July Constructed a new bridge across the spillway (steel) bridge
1992   Smithfield Fence replaced the fence at the gate house repair
1993 May Brush clearing party brush
1993 June Shaft was pulled and repairs were made to the gate structure repair
1993 June Replaced roof on gate house $950.  Wind blew old roof off repair
1993 June $250 appropriated for diver to make repairs under water repair
1994 Nov Volunteers cut brush on lake side of the dam brush
1995 Nov Volunteers cut brush on dam brush
1997 July Some work on spillway (no details)  
1998 Jul-Oct Court Order giving Pascoag Upper Dam Association control of water level & access to dam house (PUDA authority was passed on to the new Pascoag Reservoir Dam Management District).  
1999 June Idea for a special tax district was discussed at annual meeting

****

1999   Permission to do brush clearing was refused by owner  
2000 July Volunteers cut brush on dam

brush

2002 May Clean spillway & widened it to 21 feet

repair

2003 Dec American Landscaping cleared brush from dam

brush

2007 March Pascoag Upper Dam Association Resolution asking towns to create a Dam Management District

****

2008 March Stanley Tree cleared brush & trees from dam & spillway ($9,100)

brush

2008 Nov Repointed Spillway walls -  O'Donnell Masonry ($3,600)

repair

2008 Sept Had the dam treated for vegetation control by VCS ($1,200)

brush

2009 Sept Follow up vegetation control treatment by VCS ($400)

brush

2010 April

Initial meeting of the

Pascoag Reservoir Dam Management District -

By-laws Approved

 

****

2010 Aug

First Annual Budget Meeting of PRDMD

****

2010 Oct Had gate and drain pipe inspected (Innertech $1,800)  
2010   Completed a boundary and topological survey  ($4,440)  
2011 July New & Improved fencing around the gate house. - N. Smithfield Fence ($2,296)

repair

2011 Sept Vegetation control treatment by VCS ($453)

brush

2012   Filled a significant hole on left of the spillway - Many volunteers and donations of equipment and rip-rap by Mark Albert...

repair

2012 Apr Footbridge - Replace boards & Scrape & Paint - Mostly volunteers plus crane work by Stanley Tree.  (est $1,500 )

repair

2012 Oct New roof & painted gate house (Rylah $425)

repair

2013 July Emergency repair of broken gate stem.   Work was done by InnerTech.  Labor= $4,313, Material= $1,150   Total= $6,463

repair

2013 Sept Volunteers mowed top of dam

brush

2013 Sept Vegetation control treatment by VCS  ($475)

brush

2014

  Had a financial audit done - ($700)  
2014 Oct Added a guide above the gate to keep it squared up  (Innetech $2,174)  

2015

Mar Had Innertech inspect new guide - concern it may had come loose... Finding all was well  

2015

Aug Hired Innertech to install sacrificial anode -  ($544)  
2015 Aug Vegetation control treatment by VCS  ($475)

brush

2015 Nov Purchased and installed automation for opening/closing the gate.  ($5,415) - Now able to open/close with just 2 people & second person is for safety reasons. Video link
       
       
       
       

 

 

 

 